Drainage Works-Civil Works for upgrading of the Soroti-Moroto Road Project (150Km)

Contract date May 2019
Status On-going
Type of Drainage Works Grouted Stone pitching
Mortar bedding provided YES
Wall thickness (backslope, fore slope & base) 250mm
Minimum Width of base 500mm (0.5m)
Width of top edge 300mm
Total constructed to-date 3,760 square meters
Construction methodology -Excavate to required level, guided by survey team

-Shape backslopes and fore slopes

-Conduct adequate compaction if necessary

-Stones placed at base, and slopes with guide of strings and standard template made out of timber

-Mortar bedding and mortar infill in laid stones

-Proper finish and curing, etc.

Workers Mobilized 2 Engineers, 2 Foremen, 16 Masons, 32 mason-helpers & 3 support staff
Tools and equipment mobilized PPE for workers and Road Safety equipment

3No. Tipper trucks             -8No. Wheel barrows

5No. Drums (storage)       -Trowels, shovels and strings

Steel tapes, long tapes, spirit levels, etc.

One thought on “Drainage Works-Civil Works for upgrading of the Soroti-Moroto Road Project (150Km)

Leave a Reply

Your email address will not be published. Required fields are marked *

Industry Updates

Design & Build Partners